Power Generation MCQs Part 18

Power Generation MCQs Part 18

Nuclear reactors utilize the process of

Nuclear reactors utilize the process of:

  1. Fission
  2. Fusion
  3. Both of these
  4. None of these

Correct answer: 1. Fission

A diesel station supplies following loads to various consumers

A diesel station supplies following loads to various consumers:

Industrial consumers = 2000

Domestic power = 150

Commercial load = 800

Domestic lighting load = 400 kW

If maximum demand on station is 3200 kW. Then diversity factor is:

  1. 0.94 
  2. 0.97 
  3. 1.02 
  4. 1.05 

Correct answer: 4. 1.05 

Solution:

Diversity factor = (2000 + 150 + 800 + 400)/3200 = 1.05

Mechanical energy is supplied to a DC generator at rate of 5000 J/s. The generator delivers 40 at 110 V. The efficiency of generator is:

Mechanical energy is supplied to a DC generator at rate of 5000 J/s. The generator delivers 40 at 110 V. The efficiency of generator is:

  1. 92%
  2. 88%
  3. 84%
  4. 80%

Correct answer: 2. 88%

Solution:

Input power = 5000 J/s = 5000 W

————–

Output power (Po) = 110 * 40 = 4400 W

————–

Efficiency (η) = Po/Pi * 100 = 4400/5000*100 = 88%

Certain power station has an average demand of 15 MW. If plant capacity factor is 50% and load factor is 60%. The reserve capacity of plant is:

Certain power station has an average demand of 15 MW. If plant capacity factor is 50% and load factor is 60%. The reserve capacity of plant is:

  1. 2 MW
  2. 5 MW
  3. 15 MW
  4. 25 MW

Correct answer: 2. 5 MW

Solution:

From formula of Plant capacity factor

Plant capacity factor = Average demand/Plant capacity

Plant capacity = Average demand/Plant capacity factor = 15/0.5 = 30 MW

——————-

Maximum demand = Average demand/Load factor = 15/0.6 = 25 MW

——————-

Reserve capacity of plant = Plant capacity – Max.demand = 30 – 25 = 5 MW

Generally, It is a practice to keep capacity of power plant by XYZ percentage more than maximum demand for meeting future load requirements:

Generally, It is a practice to keep capacity of power plant by XYZ percentage more than maximum demand for meeting future load requirements:

  1. 15 to 20%
  2. 45 to 50%
  3. 65 to 70%
  4. 90 to 95%

Correct answer: 1. 15 to 20%