Which of following power plants will take long period in erection and installation:
- Nuclear Power Plant
- Hydro Power Plant
- Thermal
- Gas-turbine
Correct answer: 1. Nuclear power plants
Explanation: Nuclear power plants plants typically take the longest time for erection and installation. This is primarily due to the complexity of the technology involved, stringent safety regulations, and extensive testing and quality control measures required. The construction of a nuclear power plant involves multiple stages including site selection, licensing, design, procurement of specialized equipment, construction of containment structures, installation of reactor components, and rigorous testing for safety and reliability. Additionally, nuclear power plants often face public scrutiny and regulatory hurdles which can further extend the construction timeline.